Removing completed NZB form HISTORY area

Get help with all aspects of SABnzbd
Forum rules
Help us help you:
  • Are you using the latest stable version of SABnzbd? Downloads page.
  • Tell us what system you run SABnzbd on.
  • Adhere to the forum rules.
  • Do you experience problems during downloading?
    Check your connection in Status and Interface settings window.
    Use Test Server in Config > Servers.
    We will probably ask you to do a test using only basic settings.
  • Do you experience problems during repair or unpacking?
    Enable +Debug logging in the Status and Interface settings window and share the relevant parts of the log here using [ code ] sections.
Post Reply
zcott
Newbie
Newbie
Posts: 6
Joined: March 29th, 2017, 12:20 pm

Removing completed NZB form HISTORY area

Post by zcott »

Is there a way to remove completed NZB items from the HISTORY area that are older than a specific date without manually do it (ie: Click "Delete" icon then click "Remove NZB")

Under the CONFIG tab and SCHEDULING tab, I can add a schedule to "Remove failed jobs" and "Remove completed jobs" but that clears out the entire history. What I am looking for is to *Remove completed jobs after # week* or *Remove completed jobs after # days*

If not, I'm hoping it can be added in a future release.

Scheduling suggestions, with different wording...
Remove completed jobs after 1 week old
Remove completed jobs over 2 weeks old
Remove completed jobs older than 3 weeks
Or
Remove completed jobs after 10 days old
Remove completed jobs over 20 days old
Remove completed jobs older than 30 days
zcott
Newbie
Newbie
Posts: 6
Joined: March 29th, 2017, 12:20 pm

Re: Removing completed NZB form HISTORY area

Post by zcott »

Answer can be found in, Configure. Switches. Post processing. History Retention.